by LL | May 30, 2022 | Drill Pipe, DUO
430 DUO and 480 DUO results have been updated in the link below DUO Connection offers “Operation Forgiveness”, which minimizes rig non-production time and repair cost for operators DUO Inspection Results Summary DUO Brochure DUO...
by Admin | Apr 22, 2022 | Drill Pipe, DUO
DUO inspection results across all sizes in use continue to be positive. DUO Connection minimizes downtime and repair costs to the operators. A summary can be found in the link below. DUO Inspection Results Summary DUO Brochure DUO...
by Admin | Feb 22, 2021 | Drill Pipe, DUO
Recently an inspection was performed on a string of custom built 4 3/4″ drill pipe with 480 DUO connections. The results of the inspection are highlighted in this revised summary report. The report has been updated to show how Complete Group’s expertise...
by Admin | Jul 30, 2020 | Drill Pipe, DUO
586 lengths of 4 1/2″ 16.6 lbs/ft S135 400 DUO range 2 drill pipe and 100 lengths of 4 1/2″ 400 DUO heavyweight were inspected with 12 ends (<1%) needing machine shop repairs. This remains consistent with past inspection results on all sizes of the DUO...
by Nigel Greenways | Nov 8, 2019 | Drill Pipe, DUO
Complete Group is proud to have contributed to the record 8,510m TD well drilled by the Shell Canada and PD #574 teams in northern Alberta’s Duvernay formation, through the use Complete Group’s 480 DUO connection and 4-3/4” custom drill string. The Canadian record...
by Nigel Greenways | Oct 25, 2019 | Drill Pipe, DUO
The 450 DUO, designed as a high torque, field friendly 4-1/2” drill pipe connection, has been successfully deployed and inspected in the Permian Basin of West Texas, the world’s largest and most productive shale basin. The strings of Range 3 pipe were manufactured...